Archive · 1 Feb 2026
MahaRERA Grants Interest for Delayed Possession in Thane’s Sheth Zuri Project
MahaRERA has made a decision about a housing project called Sheth Zuri in Thane.
Some homebuyers complained about delays in getting their homes.
MahaRERA said that the developer should pay interest to these buyers for the delay, but only after the developer gets a special certificate (Occupancy Certificate) that says the project is complete.
The interest will be calculated based on the money the buyers have already paid.
If there are any other amounts owed, they can be adjusted against this interest.
Buyers who canceled their bookings before the agreement was signed will only get their money back, not interest.
The developer said the delays were because of things like the COVID-19 pandemic and other problems, but MahaRERA said the developer is responsible for managing these issues.
Some parts of the project are already done, but others are still under construction.
Some buyers also complained about missing amenities and other problems with their homes.
MahaRERA ordered Sheth Developers to pay interest for delayed possession to eligible homebuyers of Sheth Zuri project in Thane.
Interest payment is deferred until the developer obtains the full Occupancy Certificate for the project.
Interest rate is SBI MCLR plus 2%, calculated on the actual amount paid by the complainants.
Buyers who canceled their bookings before the agreement will only receive a refund of the principal amount, not interest.
The developer attributed delays to force majeure factors like COVID-19 and regulatory issues, but MahaRERA held the developer responsible for managing these.
- Who
- Homebuyers of Sheth Zuri project and Sheth Developers
- What
- MahaRERA's order on delayed possession and interest payment
- When
- Order pronounced on January 27, 2026
- Where
- Thane, Maharashtra
- Why
- To balance buyer relief and project completion
- Project Name
- Sheth Zuri
- Developer
- Sheth Developers
- Location
- Thane, Maharashtra
- Number of Complaints
- 26
- Interest Rate
- SBI MCLR + 2%
- Occupancy Certificate Status
- Partial (Towers C and D)
- Order Date
- January 27, 2026