Centre Sanctions ₹720 Crore Project to Evacuate Renewable Energy in Tamil Nadu
The government is helping Tamil Nadu to transport its clean energy.
This plan includes building new power lines and stations.
The whole project will be expensive, but the government will help pay for some of it.
The project aims to make it easier to use clean energy in Tamil Nadu, ensuring everyone benefits.
TANTRANSCO will manage the construction of this important system.
Centre approved project to evacuate about 4,000 MW of renewable energy capacity.
The project involves construction of 624 circuit km of transmission lines.
It includes building 2200 MVA substation capacity.
The project cost is estimated at ₹720 crore.
TANTRANSCO is the implementing agency, dividing the project into 9 packages.
- Who
- Centre and TANTRANSCO
- What
- Project for renewable energy evacuation
- When
- July 30, 2025
- Where
- Tamil Nadu
- Why
- To evacuate renewable energy capacity.
- Project
- Renewable energy evacuation
- Capacity
- 4,000 MW
- Transmission lines
- 624 circuit km
- Substation capacity
- 2200 MVA
- Project Cost
- ₹720 crore
- Implementing Agency
- TANTRANSCO