Vijay Drops Parandur Airport Plan Amid Growth Concerns

Vijay Drops Parandur Airport Plan Amid Growth Concerns
Why Vijay government scrapping Chennai's 2nd airport stalls Tamil Nadu's growth · wionews.com

Tamil Nadu has decided not to build Chennai’s second airport at Parandur.

The government says it still wants a second airport, but it wants a place that would displace fewer people and harm less farmland.

Farmers and villagers had protested because homes, fields, wetlands and water bodies could be affected.

The earlier government chose Parandur in 2022 after studying four possible locations.

Supporters of Parandur say a new airport is important for Chennai’s growing industries, cargo and passengers.

They also say cancelling the project could waste years of planning and delay jobs and investment.

As a temporary step, the government plans to expand the existing airport at Meenambakkam.

A proposed Terminal 5 could eventually help the airport handle 55 million passengers each year.

Officials must now study alternative sites and obtain the necessary approvals.

Key facts

Proposed Parandur area
5,746 acres across 13 villages
Reported project cost
One source reported Rs 29,144 crore; another cited Rs 27,400 crore
Original design
A four-phase greenfield airport with an air freight village, road projects and a proposed Metro connection
Compensation offer
The state offered 3.5 times the land’s market value and resettlement houses for displaced families
Existing airport expansion
Terminal 3 work was expected to raise annual capacity to 35 million passengers; proposed Terminal 5 would add 20 million more
Eventual stated capacity
The existing Chennai airport could reach 55 million passengers annually after Terminal 5
Alternative-site requirement
Potential locations must meet connectivity, land-acquisition, environmental-approval and displacement requirements

Quotes

Purushothaman Ravichandran

Chairman of the CII Southern region

“Regarding the shift away from Parandur, the government must swiftly identify and finalise an alternative site through technical feasibility studies. Execution at the chosen alternative site must be fast-tracked with dedicated focus to prevent project delays and ensure Chennai does not lose its competitive edge to neighboring industrial hubs”
wionews.com
“If there is genuinely no turning back, then the so-called alternative site must be identified within this year at the latest. Chennai and Tamil Nadu MUST have a new world-class international airport within the next three years”
wionews.com