3 weeks ago

Anbumani Ramadoss demands action on 60,000 pending farm power connections

Anbumani Ramadoss demands action on 60,000 pending farm power connections
Anbumani slams delay in farm power connections, says 60,000 farmers left waiting · thehansindia.com

Farmers in Tamil Nadu need electricity to run water pumps so they can water their crops.

The government has a special fast-track program, called the tatkal scheme, for giving them electricity connections.

Farmers who join this program have to pay a big deposit of money first.

A leader named Anbumani Ramadoss says more than 60,000 farmers have paid their deposits but are still waiting for electricity.

Some farmers have been waiting for more than eight months, even though the rules say it should take only 15 to 90 days.

Many farmers borrowed money to pay the deposits and now have to pay extra interest.

Without electricity, some farmers could not plant their crops during the Kuruvai growing season.

Anbumani is asking the state government to act quickly and give these farmers their electricity connections.

Key facts

Politician
Anbumani Ramadoss (PMK president)
Pending applicants
60,120 farmers
Total farmers waiting
More than 4 lakh across Tamil Nadu
Deposits collected
Around Rs 1,500 crore
Latest tatkal applicants
47,554 farmers paying over Rs 1,250 crore
2023 scheme applicants
12,566 farmers paying over Rs 250 crore
Deposit range
Rs 2.50 lakh to Rs 4 lakh
Stipulated timeframe
15 to 90 days after application

Sources