Amaravati Construction Accelerated, Key Projects by 2027
The government is speeding up the construction of Amaravati, the new capital city.
Minister P. Narayana said the 350-km Trunk Road will be finished by March 2027, and the layouts by the end of 2027.
He thanked the farmers for their help and asked them to give more land for the railway line and ring road.
The government is making sure farmers get good plots in return.
Chief Minister N. Chandrababu Naidu checks the progress every two weeks.
The MLA and MLC quarters, and ministers' residences will be ready soon.
The government is working with farmers to complete land pooling and start the construction of the inner ring road and railway track.
Construction of Amaravati's 350-km Trunk Road to be completed by March 2027.
Layouts for the capital city to be finished by the end of 2027.
MLA Quarters to be handed over by July 25, MLC Quarters by August 15, and ministers' residences by September first week.
Land pooling completed for 50 acres, with farmers submitting documents and choosing layout designs.
Inner ring road and railway track to pass through Tadikonda, Kanteru, Mothadaka, and Kopparavuru villages.
- Who
- Minister P. Narayana, Chief Minister N. Chandrababu Naidu, Farmers
- What
- Accelerated construction of Amaravati, including Trunk Road and layouts
- When
- Trunk Road completion by March 2027, layouts by end of 2027
- Where
- Amaravati, Tadikonda, Kanteru, Mothadaka, Kopparavuru villages
- Why
- To complete the construction of Amaravati capital city and related infrastructure
Government Perspective
Farmers' Perspective
Land Acquisition and Compensation
Government Perspective
The government is ensuring that land acquisition is completed efficiently and that farmers are compensated with plots in beneficial locations.
Farmers' Perspective
Farmers may have concerns about the adequacy of compensation and the suitability of the plots they will receive.
- Trunk Road Completion
- March 2027
- Layouts Completion
- End of 2027
- MLA Quarters Hand Over
- July 25
- MLC Quarters Hand Over
- August 15
- Ministers' Residences Hand Over
- September first week
- Land Pooling Status
- Documents submitted for 50 acres