Govt Extends Time for RE Projects Delayed by GIB Case
The Indian government has given extra time to some renewable energy projects that were delayed.
These projects were delayed because they needed permission to build power lines above the ground, but the permission was delayed because of a court case about a bird called the Great Indian Bustard.
The court case made it hard for the projects to get the needed permission.
The government said this delay was not the fault of the project developers and is like a big unexpected problem.
So, they are giving these projects more time to finish.
The extra time is for the period when the court case was still going on.
This will help the projects catch up on their work.
The government also said that the projects can pass on this extra time to the people who are helping them, like the companies that build the projects and supply materials.
But if a project already got extra time for another reason, that time will be taken off from the new extra time.
Also, only projects that asked for permission before December 19, 2025, can get this extra time.
Government grants time extension for RE projects delayed due to GIB case in Supreme Court.
Delay in approval for overhead power transmission lines in GIB areas treated as Force Majeure.
Extension applies to projects in Rajasthan and Gujarat from March 21, 2024 to December 19, 2025.
REIAs to grant time extension on a case-to-case basis, extending intermediate milestones accordingly.
Developers can pass on time extension benefits to stakeholders like EPC contractors and suppliers.
- Who
- Renewable energy developers in Rajasthan and Gujarat
- What
- Time extension granted for delayed RE projects due to GIB case
- When
- Effective from March 21, 2024 to December 19, 2025
- Where
- Rajasthan and Gujarat, India
- Why
- Due to pending Supreme Court case on Great Indian Bustard (GIB) affecting approvals for overhead power transmission lines
- Issue
- Delay in approval for overhead power transmission lines in GIB areas
- Affected States
- Rajasthan and Gujarat
- Affected Capacity
- 5-6 GW of RE capacity
- Time Extension Period
- March 21, 2024 to December 19, 2025
- REIAs Involved
- SECI, NTPC, NHPC, SJVN
- Legal Basis
- Section 68 of the Electricity Act, 2003
- Force Majeure
- Delay treated as Force Majeure
- Eligibility Deadline
- December 19, 2025