Kakinada Flyover Service Roads Delayed by Contractor Payment Issues
A new flyover in Kakinada is finished, but the roads leading to it are not.
The company building the roads stopped because they haven't been paid.
People are having trouble getting around because of this.
The local government says it's the state's job to pay the company, and the state says it owes money.
A local politician is trying to help, and people whose land was used for the road haven't been paid either.
The court has said that the government should pay those people before continuing the work, but the flyover was still finished.
The new flyover in Kakinada lacks service roads, causing problems for residents.
The contractor stopped road work due to unpaid bills.
Residents have petitioned the KMC to address the issue.
R&B officials state that they owe the contractor approximately Rs 2.50 crore.
A BJP leader is seeking intervention from the Municipal Administration minister to solve the issue.
- Who
- The contractor, Kakinada Municipal Corporation (KMC), Roads and Buildings (R&B) department, residents, and BJP leader Duvvuri Subrahmanyam.
- What
- The unfinished service roads near the new flyover in Kakinada.
- When
- The flyover was completed last year, but service roads remain unfinished.
- Where
- Kakinada, between Ramaraopeta and Military Road.
- Why
- The contractor stopped work due to unpaid bills, and residents are facing difficulties.
Residents/KMC
Contractor/R&B
Road Construction
Residents/KMC
Residents and KMC want the service roads completed immediately to alleviate difficulties.
Contractor/R&B
Contractor halted service road construction due to non-payment of dues.
- Location
- Kakinada, India
- Project
- Flyover construction
- Contractor's Claimed Dues
- Rs 2.50 crore
- Key Issue
- Delayed service road construction
- Involved Parties
- KMC, R&B department, residents, contractor