NHAI Moves Against PNC Infratech After Lucknow-Kanpur Expressway Slippage

NHAI Moves Against PNC Infratech After Lucknow-Kanpur Expressway Slippage
Lucknow-Kanpur Expressway suffers 300m slippage within 2 weeks; PNC faces NHAI action but its other Rs 3,483 cr projects continue · thestatesman.com

A brand-new road called the Lucknow-Kanpur Expressway opened for cars and trucks in July.

Just two weeks later, a part of the road began to sink and crack.

About 300 metres of the road was damaged near kilometre 64.

The company that built the road, PNC Infratech, is being held responsible.

The National Highways Authority of India, which looks after national highways, may stop PNC from building new roads for a while.

Some engineers and workers who looked after the project are not allowed to work on government road projects for two years.

Nobody pays tolls on the road until the damaged part is fixed.

PNC says its other road projects are fine and will continue.

A team from IIT Kharagpur, a famous engineering university, will study why the road broke.

PNC has faced problems before with other roads it built.

Key facts

Expressway
Lucknow-Kanpur Expressway (Package-II)
Corridor length
63 km
Slippage extent
About 300 metres near kilometre 64, right-hand carriageway
Timeline
Inaugurated July 13; slippage observed July 26; NHAI action announced August 5
Estimated rectification cost
About Rs 3 crore
Proposed penalty
2 per cent of performance security
Officials debarred for two years
Project Manager Vivek Kumar Gupta; Independent Engineer Team Leader Surendra Kumar; Resident Engineer Yatendra Kumar
PNC's other NHAI projects
Two NH-927 projects, combined bid project cost Rs 3,483 crore (excl. GST)