Archive · 11 Aug 2026

BMC Approves ₹24.58 Crore for Andheri-Goregaon Bridge Power Shift

BMC Approves ₹24.58 Crore for Andheri-Goregaon Bridge Power Shift

In Mumbai, the city is building a big new bridge across a creek called Goregaon Creek.

The bridge will connect Andheri West to Goregaon West.

It is a special kind of bridge held up by strong cables.

But Tata Power's big electric wires and tall towers were in the way.

The wires need to be moved before the bridge can be finished.

Moving them costs more money than the city first thought.

So the city approved extra money, ₹24.58 crore, to relocate the wires.

Now the whole bridge will cost ₹709.16 crore.

The bridge should help drivers travel with fewer traffic jams.

Construction work started in December 2025 and is currently underway.