Archive · 25 Sep 2025
Power Grid Takes Over Davanagere Transmission Project
Imagine two companies working on a power project.
One of them, RECPDCL, was in charge and then gave the project to Power Grid Corporation of India.
This handover happened on September 24, 2025.
Power Grid will now build and manage this project, which includes upgrading a power station in Davanagere.
The project is expected to cost around ₹366.26 crore and take about two years to complete.
This is a big step in making sure that power gets to where it needs to go!
RECPDCL handed over Davanagere Power Transmission Limited to Power Grid.
The handover occurred on September 24, 2025.
Power Grid is the Transmission Service Provider.
The project involves upgrading the Davanagere PS.
The project's cost is approximately ₹366.26 crore.
- Who
- RECPDCL and Power Grid Corporation of India Limited.
- What
- Handover of the Davanagere Power Transmission project.
- When
- September 24, 2025.
- Where
- Davanagere, India
- Why
- To facilitate the development of the transmission project.
RECPDCL
Power Grid
Project Ownership
RECPDCL
RECPDCL initiated the project and managed the bidding process.
Power Grid
Power Grid Corporation is now responsible for the project's development and operation.
- Project Handover
- RECPDCL handed Davanagere Power Transmission Limited to Power Grid Corporation of India Limited.
- Date of Handover
- September 24, 2025
- Project Cost
- Approximately ₹366.26 crore
- Implementation Period
- 24 months
- Project Scope
- Augmentation of transformation capacity at Davanagere PS.