Mumbai: BMC to Resume Road Concretisation from October 1st
The Mumbai government is restarting its work on building concrete roads after a break during the rainy season.
They will start again on October 1st, and they will let everyone know in advance which roads will be worked on.
The list of roads will be available on August 15th.
The goal is to finish all the concrete roads by the end of 2027.
Officials are also working on solving complaints from citizens and dealing with parking issues.
BMC to resume road concretisation work in Mumbai from October 1.
Road works list will be published on August 15 on the BMC website.
Concretisation will first resume on roads left halfway, then new roads.
The entire road concretisation project is expected to be completed by the end of 2027.
The BMC commissioner directed officials to address citizen complaints and manage parking issues.
- Who
- BMC (Brihanmumbai Municipal Corporation)
- What
- BMC to resume road concretisation works.
- When
- Work resumes October 1st, list published August 15th, project end of 2027.
- Where
- Mumbai
- Why
- To make city roads pothole-free.
- Project Start
- July 2022
- Roads planned
- 2,121
- Total Length Planned
- 698.44 kms
- Percentage Completed
- 49%
- Road works to resume
- 614
- Completion Deadline
- End of 2027