Goodman Withdraws Sydney AI Data Centre Plan Amid Backlash

Goodman Withdraws Sydney AI Data Centre Plan Amid Backlash
Goodman Scraps Sydney AI Facility Plan As Data Centre Boom Faces Community Backlash In Australia · freepressjournal.in

Goodman Group planned to build a large AI data centre in Lane Cove, Sydney.

The centre would have operated all day and night.

People living nearby and a local school community objected to the plan.

They worried about safety, property values, infrastructure costs and effects on the neighbourhood.

Some Australians have also raised concerns about noise and diesel generators at other data centre projects.

Goodman said it withdrew the application after reviewing community feedback and regulatory changes.

The company had estimated the project would cost A$443.8 million.

Experts say public opposition may slow down or change future data centre developments.

Australia still has a very large pipeline of planned data centre investment.

Key facts

Project
Project Mars, a proposed 24-hour AI data centre
Location
Lane Cove, Sydney, Australia
Estimated development cost
A$443.8 million
Share-price reaction
Goodman shares fell as much as 2.1% in Sydney trading
Australian data centre pipeline
About A$175 billion
Expected investment
Around A$110 billion over the next three years, according to Westpac Banking Corp analyst Pat Bustamante
Policy response
Victoria restricted data centres in residential areas and required new facilities to secure their own renewable energy supply

Quotes

Naomi Wagura

Accela Research researcher discussing the effects of community resistance on Australian data-centre development

“We expect community opposition to delay some projects, force redesigns and influence where investment flows”
freepressjournal.in