NGT Extends Deadline for ACC Cement Pollution Report
The National Green Tribunal (NGT) has given a joint committee four more weeks to submit a report about air pollution from an ACC Cement plant in Barmana, Himachal Pradesh.
A man named Kashmir Singh complained about the pollution.
The committee said they were delayed because they didn't get all the reports on time.
The NGT also allowed one member, Dr. Narender Sharma, to submit his report separately.
Earlier, the Himachal Pradesh State Pollution Control Board (HPSPCB) said they plan to use money from the cement company to improve the environment.
They want to build things like better water systems and waste management.
The cement company said they are following the committee's advice to keep the air clean.
The next hearing is in February 2026.
NGT grants four-week extension to joint committee for submitting report on ACC Cement plant's alleged air pollution.
Complaint filed by Kashmir Singh alleging air pollution due to ACC Cement plant operations in Barmana.
Joint committee delayed report submission due to late receipt of technical expert report and email from Dr. Narender Sharma.
HPSPCB proposed using environmental compensation funds for water resource development and solid waste management.
ACC Cement Ltd deposited Rs 20 lakh each with CPCB and HPSPCB as environmental compensation.
- Who
- Kashmir Singh (complainant), NGT, ACC Cement Ltd, Himachal Pradesh State Pollution Control Board (HPSPCB), Central Pollution Control Board (CPCB)
- What
- NGT grants extension to joint committee for submitting report on alleged air pollution by ACC Cement plant
- When
- Order passed on Wednesday, next hearing on February 12, 2026
- Where
- Barmana, Bilaspur district, Himachal Pradesh
- Why
- To address allegations of air pollution caused by ACC Cement plant operations
- Location
- Barmana, Bilaspur district, Himachal Pradesh
- Complainant
- Kashmir Singh
- Respondents
- State of Himachal Pradesh, Environment Department, ACC Cement Ltd
- Joint Committee Members
- Two members (unnamed) and Dr. Narender Sharma
- Environmental Compensation
- Rs 20 lakh each to CPCB and HPSPCB
- Proposed Projects
- Water resource development, solid waste management, solar street lights, hand pumps
- Next Hearing Date
- February 12, 2026