RERA Orders ₹14.5 Lakh Refund After Gurugram Project Registration Revoked

RERA Orders ₹14.5 Lakh Refund After Gurugram Project Registration Revoked

A homebuyer paid ₹14.5 lakh for a flat in a Gurugram housing project.

The flat was supposed to be built in Dhanwapur village.

Construction stopped, according to the buyer.

The buyer said the builder still asked for more instalments.

He refused to pay more and asked for his money back.

The builder did not provide the refund, so he complained to Haryana RERA.

Haryana RERA found that the project's registration had been revoked.

It ordered the builder to return all the money with 10.80% yearly interest.

The builder has 90 days to follow the order or face legal consequences.