Archive · 21 May 2025
JSW Energy Invests to Expand Renewable Energy Capacity
Imagine a company called JSW Energy that wants to make more clean energy.
They bought another company, O2 Power, to help.
JSW Energy plans to spend a lot of money, about ₹14,000 crore, to build more solar and wind farms.
They hope to have much more clean energy by 2027.
They are also working on other projects, including a thermal power plant.
This means they are investing in different ways to create electricity.
JSW Energy will invest ₹14,000 crore to expand O2 Power's renewable energy capacity to 4.7 GW by June 2027.
JSW Neo Energy Ltd acquired O2 Power for ₹12,468 crore.
2,259 MW of O2 Power will be operational by June 2025.
JSW Energy is constructing 11.3 GW of generation projects, fully tied up under long-term PPAs.
The company is also investing in a 1.6 GW thermal power project.
- Who
- JSW Energy.
- What
- JSW Energy plans to invest in expanding renewable energy capacity of O2 Power.
- When
- By June 2027.
- Where
- N/A
- Why
- To expand its renewable energy capacity.
- Investment to expand renewable energy capacity
- ₹14,000 crore
- Targeted renewable energy capacity by 2027
- 4.7 GW
- JSW Neo Energy Ltd acquired O2 Power for
- ₹12,468 crore
- Current installed capacity of O2 Power
- 1.3 GW
- Generation projects under construction
- 11.3 GW
- Salboni ultra-supercritical thermal power project
- 1.6 GW
- Capex plan for FY26
- ₹15,000-18,000 crore