NHAI Widens Road Near Subroto Park to Ease Dhaula Kuan Traffic
Imagine a road where traffic gets really stuck because it suddenly becomes narrower, like a funnel.
This is happening near the Subroto Park Air Force Station in Delhi.
The National Highways Authority of India (NHAI) is widening a part of this road that was only two lanes wide to make it four lanes.
This narrow spot was causing big traffic jams, especially for people going to the airport.
They are also moving some things like drains and a building to make space.
In addition to making the road wider, they are building a new bridge for people to walk over safely.
The work should be done in about six months, and it should make it much easier for cars to travel between Dhaula Kuan and the airport.
They are also trying to be good to the environment by planting trees and using special machines to reduce dust during construction.
NHAI has started widening a road near Subroto Park Air Force Station from 2 lanes to 4 lanes on the left-hand side towards Gurugram.
The project aims to eliminate a traffic bottleneck at the Parade Road underpass that causes significant delays, especially for airport-bound vehicles.
The narrowing of the road to two lanes was caused by a Metro pillar.
The project is expected to be completed in approximately six months and will improve connectivity between Dhaula Kuan and Delhi Airport.
Enhancements include a new Foot Over Bridge (FOB) for pedestrian safety, an improved drainage system, and environmental measures like tree transplantation and pollution control.
- Who
- National Highways Authority of India (NHAI)
- What
- Widening of a carriageway from two to four lanes to eliminate a traffic bottleneck.
- Where
- Near Subroto Park Air Force Station, on the left-hand side towards Gurugram, impacting traffic flow from Dhaula Kuan towards Delhi Airport.
- When
- Work commenced recently, with an estimated completion in about six months.
- Why
- To improve traffic flow and enhance connectivity between Dhaula Kuan and Delhi Airport by removing a major choke point at the Parade Road underpass.
Key facts
- Project Goal
- Improve traffic flow and connectivity between Dhaula Kuan and Delhi Airport by widening a bottleneck.
- Road Section
- Left-hand side (LHS) towards Gurugram, near Subroto Park Air Force Station.
- Widening Details
- From 2 lanes to 4 lanes.
- Reason for Bottleneck
- Metro pillar narrowing the road to 2 lanes from 4 lanes.
- Estimated Completion
- About six months.
- Additional Features
- New Foot Over Bridge (FOB), enhanced drainage system, tree transplantation, anti-smoke guns, water sprinklers.
- Traffic Management
- Traffic marshals, tow-away cranes, and safety cones.
Timeline
GMDA planned an underpass at AIT Chowk for traffic relief.
Construction caused jams; authorities widened nearby roads.
Officials are further expanding routes at Char Murti, Tigdi.
NHAI also widens a section near Subroto Park for airport access.
Quotes
NHAI
National Highways Authority of India
“In order to improve traffic flow and enhance connectivity between Dhaula Kuan and Delhi Airport, NHAI has undertaken widening of the carriageway on LHS (towards Gurugram) from 2 Lane to 4 Lane at the Subroto Park Air Force Station in New Delhi.”
news18.com
“The project also includes construction of a new Foot Over Bridge (FOB) near Subroto Park Air Force Station at the starting of RTR flyover, for enhancing safety and providing better connectivity to pedestrians.”
news18.com
Ministry of Road Transport and Highways
The Ministry of Road Transport and Highways
“The project will help to remove the traffic bottleneck on the left side of the road at the start of Parade Road underpass, where traffic movement is currently restricted towards Gurugram from Delhi.”
thestatesman.com
Sources
From Ayodhya to Sikkim: Delhi's 41 Roundabouts to Tell India's Story
NHAI undertakes project to remove traffic bottleneck at Subroto Park Airforce Station in Delhi
With focus on India’s cultural heritage, PWD announces themed revamp of 41 key roundabouts
Dhaula Kuan Traffic Snarls To End In 6 Months: NHAI Begins Road Widening Work Near Subroto Park