SLBC Tunnel Completion Delayed by One Year

SLBC Tunnel Completion Delayed by One Year

The SLBC tunnel project in Hyderabad is taking longer to finish than originally planned.

The government thought it would be done by January 2028, but now it looks like it will take until January 2029.

There are still about 9.6 kilometers of tunnel left to dig, but that might increase by another 1-2 kilometers.

Workers will dig from both ends of the tunnel using a method called drill-and-blast.

They expect to dig about 300 meters each month.

There was a big problem in February 2025 when part of the tunnel collapsed, and eight workers died.

Only two bodies were found, and the others are still missing.

Before they can start digging again, they need to fix the collapsed part.

This means the project will take about three more years to finish.