Central Railway Blocks Panvel Services for Redevelopment
The Central Railway in Mumbai is stopping some train services at Panvel station from December 25 to December 31.
They are doing this to make improvements like building new footbridges and moving some tracks.
Many long-distance trains will be delayed, rescheduled, or diverted during this time.
For example, the train from Mangaluru to CSMT will be delayed for 20 to 30 minutes every day.
Another train, the Daund–Gwalior Express, will take a different route and stop at Kalyan instead of Panvel.
The railway asks passengers to check the changes and be patient with the delays.
Central Railway will block train services at Panvel station from December 25 to December 31 for redevelopment works.
Several long-distance mail and express trains will be regulated, rescheduled, or diverted during the block period.
The 12134 Mangaluru Junction–CSMT Express will be delayed for 20 to 30 minutes daily.
The 22193 Daund–Gwalior Express will be diverted via Karjat–Kalyan–Bhiwandi Road and will halt at Kalyan instead of Panvel.
The works include removing infringements, shifting a track point, launching foot overbridge girder sets, and erecting steel columns and cross girders.
- Who
- Central Railway’s Mumbai division
- What
- Blocking train services at Panvel station for redevelopment works
- When
- December 25 to December 31
- Where
- Panvel station
- Why
- To carry out works linked to the Panvel–Kalamboli Coaching Complex and station redevelopment
- Block Period
- December 25 to December 31
- Affected Trains
- 12134, 01151, 01152, 22655, 11099, 22114, 22149, 22193
- Key Works
- Removal of infringements, shifting of Point No 101B, launching of foot overbridge girder sets, erection of steel columns and cross girders
- Impacted Lines
- Up and down Mail lines, loop lines, Karjat lines, engine reversal lines, platforms 6 and 7
- Diverted Train
- 22193 Daund–Gwalior Express (via Karjat–Kalyan–Bhiwandi Road)