MCD Commissioner Flags Delays in CAQM Road Works Before Pollution Season

MCD Commissioner Flags Delays in CAQM Road Works Before Pollution Season

The Municipal Corporation of Delhi is repairing many roads before the city’s high-pollution months.

Officials checked the projects and said the work was moving too slowly.

About 689 kilometres of roads are finished.

Another 193 kilometres are being worked on.

Some planned projects have not yet been awarded to contractors.

The city also needs Rs 553 crore more for 531 projects.

Engineers must check the work every day and fix problems quickly.

Concrete roads are supposed to finish by October 31, while bituminous roads are due by November 15.