SLBC Tunnel Clears Difficult Geological Stretch as Excavation Advances

SLBC Tunnel Clears Difficult Geological Stretch as Excavation Advances

Workers building the SLBC tunnel have passed through a very difficult section of rock.

They dug 700 metres over the last five to six months, working from both ends.

The tunnel is nearly 44 kilometres long and is about 79 per cent finished.

Some areas were unstable, so workers slowed down to improve safety.

The irrigation minister asked officials and the contractor to keep work moving while protecting the crews.

Concrete lining is already being added to finished parts.

The project is intended to bring water from the Srisailam reservoir to drought-prone areas.

Officials are working toward delivering water by June 2028.