Archive · 10 Aug 2025
Delhi's E-Waste Eco Park Expansion Doubles Capacity After Norway Study
Delhi's e-waste recycling center is getting a major upgrade.
Inspired by a similar facility in Norway, the Holambi Kalan plant will become twice as big, handling more electronic waste.
The project will also cost nearly double the original amount, with increased funding.
The upgraded plant will adopt a zero-waste model, meaning no pollution, using advanced cleaning technologies.
This expansion aims to promote a cleaner, more sustainable Delhi and a circular economy by recovering valuable materials.
Delhi's E-Waste Eco Park in Holambi Kalan will double its capacity.
The expansion follows a visit to an e-waste facility in Norway.
The plant will now handle 1.1 lakh metric tonnes of e-waste annually.
Investment will nearly double to around Rs 300 crore.
The park aims for zero waste using advanced technologies.
- Who
- Delhi's Environment and Industries Minister Manjinder Singh Sirsa and Delhi government.
- What
- Expansion of Delhi's E-Waste Eco Park.
- When
- The announcement was made after an inspection in Norway.
- Where
- Holambi Kalan, Delhi.
- Why
- To increase capacity and adopt zero-waste practices.
- Original Capacity
- 51,000 metric tonnes annually
- Revised Capacity
- 1.1 lakh metric tonnes annually
- Original Investment
- Rs 150 crore
- Revised Investment
- Rs 300 crore (approx.)
- Location
- Holambi Kalan
- Key Principle
- Global zero-waste model
- Revenue Projection
- Over Rs 500 crore