Haryana builder ordered to hand over flat after eight-year delay

Haryana builder ordered to hand over flat after eight-year delay

A 73-year-old man paid a builder Rs 19.62 lakh for a flat.

He was supposed to receive the flat by 2019, but possession was not given.

The builder said the buyer had stopped paying instalments and that Covid-19 delayed construction.

The consumer commission disagreed with the builder’s explanation.

It said the delay began before the pandemic and lockdown.

The commission ordered the builder to finish the work and give the man the flat within 30 days.

The builder must also pay interest on the money kept since November 2018.

It must additionally pay Rs 2.10 lakh for the man’s hardship and legal costs.