2 days ago
ACME Solar Commissions Solar and Battery Storage Projects in Rajasthan
ACME Solar has started operating two new clean-energy facilities in Rajasthan.
One facility produces electricity from 66.68 megawatts of solar power.
It is the first phase of a larger solar project planned to reach 300 megawatts.
The larger hybrid project is also expected to include 100 megawatts of wind power.
The company also switched on a battery storage facility holding 300 megawatt-hours of energy.
Batteries can store electricity and provide it when needed.
This storage project is part of a much larger planned system.
ACME Solar says its operating renewable-energy capacity is now about 3,057 megawatts, with 4.16 gigawatt-hours of battery storage.
The company expects to finish the remaining projects in stages.
ACME Solar commissioned 66.68 MW of solar capacity at Kelan village in Bikaner, Rajasthan.
The solar facility is Phase I of a planned 300 MW solar project that will also include 100 MW of wind capacity.
The company separately commissioned 53.63 MW/300 MWh of BESS capacity at the same site.
The BESS project has a planned total capacity of 300 MW/1,581 MWh and is backed by a PPA with SJVN Limited.
ACME Solar’s operational portfolio now stands at approximately 3,057 MW of renewable energy and 4.16 GWh of BESS capacity.
- Who
- ACME Solar Holdings and its subsidiaries ACME Renewtech and ACME Greentech Seventh.
- What
- Commissioning of 66.68 MW of solar capacity and 53.63 MW/300 MWh of battery storage capacity.
- Where
- Kelan village in Bikaner, Rajasthan.
- When
- The report provides no calendar date; the company expects to complete the solar project by the end of the third quarter of FY27 and the full BESS project by the third quarter of the current financial year.
- Why
- To expand ACME Solar’s operational renewable-energy and battery-storage portfolio through solar, hybrid, and firm renewable-energy projects.
Key facts
- Solar capacity commissioned
- 66.68 MW
- Planned solar capacity
- 300 MW
- Planned wind capacity
- 100 MW
- BESS capacity commissioned
- 53.63 MW/300 MWh
- Planned BESS capacity
- 300 MW/1,581 MWh
- Operational renewable capacity
- Approximately 3,057 MW
- Operational BESS capacity
- 4.16 GWh