Archive · 15 Jan 2026
Delhi Extends Barapullah Phase 3 Deadline to 2027
The Delhi government has extended the completion deadline for the Barapullah Phase 3 project to 2027.
This project, which started in 2015, aims to connect Sarai Kale Khan to Mayur Vihar.
The government says the delay is due to things like land acquisition and moving high-tension lines, which they couldn't control.
The project was supposed to be done by 2017, but it's taken much longer.
The cost has also gone up by Rs 374.40 crore, making the total cost Rs 1,653.03 crore.
The government is taking steps to make sure the project finishes on time and doesn't cost more than necessary.
They will set up a committee to monitor the project closely.
Delhi government extends Barapullah Phase 3 project deadline to 2027.
Initial deadline was 2017, with the project starting in 2015.
Cost escalation of Rs 374.40 crore, total cost now Rs 1,653.03 crore.
95% of the work is completed, with 15 more months needed to finish.
Delays attributed to land acquisition and shifting of high-tension lines.
- Who
- Delhi government and Public Works Department (PWD)
- What
- Extension of Barapullah Phase 3 project deadline to 2027
- When
- Initial deadline was 2017, new deadline is 2027
- Where
- Delhi, India
- Why
- Due to factors beyond control such as land acquisition and shifting of high-tension lines
- Project
- Barapullah Phase 3
- Initial Deadline
- 2017
- New Deadline
- 2027
- Initial Cost
- Rs 1,260.63 crore
- Current Cost
- Rs 1,653.03 crore
- Cost Increase
- Rs 374.40 crore
- Completion Percentage
- 95%
- Remaining Time
- 15 months