Punjab Power Shortage Triggers Long Industrial Electricity Cuts

Punjab Power Shortage Triggers Long Industrial Electricity Cuts
Punjab power crisis hits industry as Ludhiana, Jalandhar face 8-10 hour cuts. Here's what is happening in the state · livemint.com

Punjab does not currently have enough electricity to meet demand.

Two units at private power plants stopped working, reducing supply by about 1,360 MW.

At the same time, very hot weather increased the need for electricity.

Punjab’s peak demand was much higher than during the same period last year.

Some factories are losing power for 8 to 10 hours each day.

Homes and farms in some areas are also facing shorter unscheduled cuts.

Officials say they are buying electricity where possible and expect restrictions to end when supply improves.

Industry representatives say one planned weekly closure would be less damaging than daily power cuts.

Key facts

Industrial outage duration
About 8 to 10 hours in major industrial centres; some accounts cited cuts of 10 to 12 hours daily.
Affected industrial centres
Ludhiana, Jalandhar, Amritsar and Mohali.
Generation loss
Approximately 1,360 MW after one unit each at two private thermal plants became non-functional.
Peak demand
16,519 MW on Saturday, compared with 12,489 MW during the corresponding period last year.
Reported current demand and availability
The Punjab government cited demand of about 17,000 MW and availability of about 14,000 MW, a 3,000 MW gap.
Other affected consumers
Domestic and agricultural consumers in several areas are facing about 3 to 4 hours of unscheduled cuts.
Affected network
Restrictions were imposed on consumers not connected to 66-KV lines.

Quotes

Tarunpreet Singh Sond

Punjab Cabinet Minister

“I have spoken to several industrialists on this issue, and the common view is that instead of imposing 10-12-hour power cuts on a daily basis, it would be better if the government asked industries to shut down for one full day every week. Daily power cuts of 10-12 hours would cost us dearly. We are already in discussion with the power minister over this issue.”
livemint.com
“The current demand in Punjab is 17,000 MW. Our current power availability is around 14,000 MW, which is a 3,000 MW shortage. The three main tasks are to highlight the 1,000 MW of power we receive from the central government, which is our right as Punjab. This time, we are not getting 1,000 MW of power from the central government.”
livemint.com