Archive · 2 Feb 2026
Yelahanka Flyover Set for September 2026 Completion
The Yelahanka flyover in Bengaluru is almost done.
The boss in charge, Maheshwar Rao, said it should be finished by September 2026.
Right now, 70% of the 2-kilometre flyover is built.
They have made 51 out of 56 pillars and put 351 out of 447 parts in place.
The work is happening at night because the road is very busy.
Rao told the workers to hurry up and finish on time.
He also checked other projects like a road called Hennur–Bagalur, where they are making the road smoother.
He wants the rest of the work to be done quickly.
Rao also found two big pieces of land that will be turned into a playground and a park for people to use.
He wants the city to take over the land and start building soon.
There was also a bridge near the train tracks that needs more land to be finished.
Rao said to fix that problem fast so the bridge can be done.
Yelahanka flyover is 70% complete with 51 out of 56 pillars built and 351 out of 447 precast segments installed.
Chief Commissioner Maheshwar Rao set a deadline of September 2026 for the flyover's completion.
Work on the Hennur–Bagalur Road's white-topping is underway, with 4 km of one side completed and the rest to be finished in 15 days.
A 5-acre plot near Hennur Bande will be transferred to the city corporation for development into a playground.
A 3-acre parcel in HBR Layout 1st Stage will be developed into a vending zone and a central park.
- Who
- Chief Commissioner of Greater Bengaluru Authority (GBA), Maheshwar Rao
- What
- Reviewed progress on Yelahanka flyover and other infrastructure projects
- When
- During an inspection tour
- Where
- Bengaluru North City Corporation limits
- Why
- To ensure timely completion of infrastructure projects
- Project
- Yelahanka flyover
- Completion Deadline
- September 2026
- Current Completion
- 70%
- Total Pillars Planned
- 56
- Pillars Completed
- 51
- Precast Segments Planned
- 447
- Precast Segments Installed
- 351
- Hennur–Bagalur Road White-topping
- 5 km stretch
- Land Transfer for Playground
- 5-acre plot near Hennur Bande
- Land for Vending Zone and Park
- 3-acre parcel in HBR Layout 1st Stage