Archive · 21 Jun 2025
Bajel Projects Wins Ultra-Mega Power Transmission Order
Imagine a company called Bajel Projects got a big job!
They're building a super strong wire to carry electricity.
This wire is like a highway for power, stretching 138 kilometers from Mahan to Rewa.
It's a very important job, worth a lot of money – over ₹400 crore!
This company will build everything, from start to finish, in about 29 months.
This wire helps bring electricity from a power plant to where it's needed, making sure everyone has lights and can use their electronics.
Bajel Projects secured a power transmission order from PowerGrid Corporation of India.
The order is worth ₹400 crore or above, categorized as 'Ultra-Mega'.
The project involves a 138 km, 400 kV double-circuit transmission line.
The line will connect Mahan to Rewa in Madhya Pradesh.
The project is an EPC and must be completed within 29 months.
- Who
- Bajel Projects Limited and PowerGrid Corporation of India Limited (PGCIL).
- What
- Bajel Projects secured a power transmission order.
- When
- The project is to be executed within 29 months from the award.
- Where
- The transmission line will connect Mahan to Rewa in Madhya Pradesh.
- Why
- To evacuate power from the Mahan Energen Limited Generating Station.
- Company
- Bajel Projects Limited
- Client
- PowerGrid Corporation of India Limited (PGCIL)
- Project Type
- 400 kV double-circuit transmission line
- Location
- Mahan to Rewa, Madhya Pradesh
- Order Value
- ₹400 crore or above
- Project Length
- 138 km
- Contract Type
- EPC (Engineering, Procurement, and Construction)
- Timeline
- 29 months