Archive · 7 Oct 2026

Karimnagar Technically Charges First Indoor 33/11 kV Power Substation

Karimnagar Technically Charges First Indoor 33/11 kV Power Substation

Karimnagar has switched on its first indoor electricity substation.

It is at Telangana Chowk and was built on a small plot of land.

The project cost ₹6.92 crore.

Two transformers will help send electricity through six feeders at first.

The substation gets power from the Vavilalapalli and Padmanagar substations.

Digital systems let staff monitor it from a control centre and help them find problems faster.

Officials expect it to reduce pressure on three other substations in the city.

Another indoor substation is planned at the Collectorate.