Bengaluru builder to demolish tilted tower
A builder in Bengaluru, India, has decided to demolish and rebuild an 18-storey residential tower because it has a slight tilt.
The company that demolished the Supertech Twin Towers in Noida will handle the demolition.
The tower, called Block E-3 at SNN Raj Etternia, has a problem with its foundation.
The builder found this issue during final checks before giving the apartments to buyers.
The demolition will take about 5-6 months, and rebuilding will take around 18 months.
The builder will pay for the demolition and rebuilding, which will cost about ₹20 crore.
They will also give money to the 49 affected homebuyers to help with their mortgage payments and rent while they wait for their new apartments.
The homebuyers were initially upset but understand why the builder is doing this.
This is different from other cases where buildings were demolished because they broke rules.
In this case, the builder found the problem themselves and decided to fix it before giving the apartments to buyers.
SNN Raj Corp will demolish and rebuild Block E-3 at SNN Raj Etternia in Bengaluru due to a structural tilt.
Edifice Engineering, the company that demolished the Supertech Twin Towers, will handle the demolition.
The demolition will take 5-6 months, and rebuilding will take 18 months.
The total cost of the demolition and rebuilding is expected to be ₹20 crore.
The company will provide financial compensation to the 49 affected homebuyers during the reconstruction period.
- Who
- SNN Raj Corp, Edifice Engineering, 49 homebuyers
- What
- Demolition and rebuilding of a tilted 18-storey residential tower
- When
- Demolition to take 5-6 months, rebuilding in 18 months
- Where
- Bengaluru, India
- Why
- Structural tilt detected during final quality inspections
Developer's Perspective
Homebuyers' Perspective
Demolition Decision
Developer's Perspective
The developer decided to demolish the tower to ensure long-term safety and avoid future risks for homebuyers.
Homebuyers' Perspective
Homebuyers were initially disappointed but appreciated the developer's decision after understanding the long-term risks.
- Location
- Bengaluru, India
- Developer
- SNN Raj Corp
- Demolition Company
- Edifice Engineering
- Affected Tower
- Block E-3 at SNN Raj Etternia
- Number of Affected Homebuyers
- 49
- Demolition Duration
- 5-6 months
- Rebuilding Duration
- 18 months
- Total Cost
- ₹20 crore