Imagine a big prize for cleaning up and rebuilding a very crowded neighborhood called Dharavi.
A company from Dubai, called SecLink, said they were the best and offered the most money to win the prize.
But then, the people in charge cancelled the first contest and changed the rules.
SecLink says these new rules were made so they couldn't enter anymore, even though they think they still met the old rules.
They took their complaint to a high court, which didn't agree with them.
Now, SecLink has gone to the highest court in India to say the contest wasn't fair.
The government says they changed the rules because they needed to include some extra land.
Another company, Adani Group, eventually got the job to rebuild Dharavi.
Dubai-based SecLink Technologies Corporation has approached the Supreme Court regarding the Dharavi redevelopment project.
SecLink alleges it was the highest bidder in the original 2018 tender but the process was cancelled and rules were changed.
The firm claims the revised criteria in the subsequent tender made them ineligible to participate.
SecLink previously filed a petition in the Bombay High Court, which was rejected.
The Dharavi redevelopment project was eventually awarded to the Adani Group, who, along with the Maharashtra government, have denied SecLink's allegations.
- Who
- SecLink Technologies Corporation (Dubai-based firm), Adani Group, Maharashtra Government
- What
- SecLink Technologies Corporation has approached the Supreme Court alleging unfair practices in the bidding process for the Dharavi redevelopment project, claiming rules were changed after they were declared the highest bidder.
- When
- Original bidding process in 2018/2019; new tender issued two years later; matter reached Supreme Court recently.
- Where
- Dharavi, Mumbai
- Why
- SecLink alleges the rules were changed to prevent them from participating in the re-tender after they had initially emerged as the highest bidder, leading to the project being awarded to the Adani Group.
SecLink Technologies Corporation
Maharashtra Government
Bid Cancellation and Rule Changes
SecLink Technologies Corporation
SecLink alleges the original bid process was cancelled and rules were changed after it was declared the highest bidder, making it ineligible for the re-tender. They claim the changes did not reflect any real change in scope and they were prepared to meet new criteria.
Maharashtra Government
The Maharashtra government cited the need to include adjoining railway land as the reason for cancelling the original tender and issuing a new one.
Participation in New Tender
SecLink Technologies Corporation
SecLink claims it was prevented from participating in the new tender despite being prepared to meet or surpass all terms, including payments to Indian Railways.
Maharashtra Government
The government's revised criteria in the new tender made SecLink ineligible.
- Project Location
- Dharavi, Mumbai
- Project Area
- Nearly 2.4 square kilometers
- Original Bidder Allegations
- SecLink Technologies Corporation claims it was the highest bidder in 2018/2019.
- Awarded to
- Adani Group
- SecLink's Claimed Bid Amount
- Around Dh3 billion (approx. $817 million)
- SecLink's Prepared Bank Guarantee
- $4 billion (Dh13.5 billion)