A new bridge for the Mumbai-Ahmedabad Bullet Train has been completed over the Sabarmati River in Ahmedabad.

It is 480 metres long and about 36 metres tall.

The height helps the rail route clear nearby roads, bridges, metro corridors and railway lines.

The bridge stands on eight large piers.

Its longer spans mean fewer piers are needed in the riverbed.

Workers built it in sections from the piers, joining the sections to form the bridge deck.

This method did not need temporary supports beneath the deck.

The bridge is one of 21 planned river bridges in Gujarat, and 18 are now complete.