Sewri-Worli connector delayed to early 2027

Sewri-Worli connector delayed to early 2027

The Sewri-Worli connector and the reconstructed Elphinstone bridge in Mumbai are going to be delayed.

The new deadline is early 2027 instead of September 2026.

The delay is because of many things like taking longer to dismantle the old bridge, unexpected work, complaints from residents, not enough workers, and the rainy season.

The bridge is 132 meters long and needs 90 days to assemble and one week to slide into place.

The MMRDA and J Kumar are working on it, but there are also complaints about pollution, blocked footpaths, and buildings shaking.

They are trying to fix all these problems and get more workers.