Bombay High Court Upholds Dargah Demolition Order
The Bombay High Court said "no" to a group that built a religious building (Dargah) without permission.
The building was much bigger than it was supposed to be, and the group didn't have the right paperwork.
The court said they couldn't just claim the land, and they had to prove it was theirs.
They also didn't get the permits to build.
The group claimed the Dargah was there before, but the court didn't believe them and said they had to take it down in two weeks.
The court also noted they did not attend the hearings from the municipality.
Bombay High Court dismissed a plea challenging demolition of an illegal Dargah in Thane.
The Dargah expanded from 160 sq. ft. to 17,610 sq. ft. without municipal approval.
The court stated that the Trust's claim of the Dargah's legality was not supported.
The court noted the Trust failed to provide evidence of ownership or construction permissions.
The court ordered the Dargah's demolition within two weeks of the order's posting.
- Who
- Gazi Salauddin Rehmatulla Hoole, alias Pardeshi Baba Trust
- What
- Bombay High Court dismissed a plea regarding the demolition of an illegal Dargah.
- When
- The Bombay High Court made the ruling on July 9, 2025. The Supreme Court order was from July 17, 2025.
- Where
- Thane, Maharashtra
- Why
- The court found that the Dargah was built without permission and on usurped land.
Trust's Perspective
Court's Perspective
Historical Existence
Trust's Perspective
The Dargah existed before 1982.
Court's Perspective
The court found no merit in this claim.
Legal Flaws
Trust's Perspective
They argued that the High Court didn't consider the dismissal of a civil suit related to the Dargah.
Court's Perspective
The court stated that dismissal of a suit does not confirm any right.
Size of Dispute
Trust's Perspective
They claimed only 3,600 sq. ft. of construction was disputed.
Court's Perspective
The court found no construction permissions and no ownership.
- Court
- Bombay High Court
- Date of Order
- July 9, 2025
- Building Size (original)
- 160 sq. ft.
- Building Size (expanded)
- 17,610 sq. ft.
- Action
- Demolition ordered within two weeks
- Legal Remedy
- Supreme Court directed the Trust to avail appropriate legal remedy