India's AI Data Centres to Add 26.3 GW Load by 2031-32
The Ministry of Power in India has announced that AI data centres will add a huge amount of electricity demand, about 26.3 gigawatts, by the year 2031-32.
This is almost double what was previously estimated.
The government is talking to different groups to make sure there is enough reliable power and to balance the grid, as data centres can use a lot of electricity in short bursts.
Some people think data centres should be built near cities for better connections, while others believe they should be near green energy sources to avoid problems with the power grid.
India's digital economy is growing fast, and this means more data centres are needed to support things like AI and online transactions.
Experts are worried about how this extra demand will affect the stability of the power grid.
AI data centres will add 26.3 GW load by 2031-32, almost double the previous estimate.
The Ministry of Power is consulting with stakeholders to ensure reliable power supply and grid stability.
Discussions are ongoing about locating data centres away from urban centres to avoid transmission congestion.
India's data centre capacity is projected to grow significantly, with AI-dedicated capacity expected to expand nearly 24-fold by 2030.
Experts have raised concerns about the potential risks to grid stability due to the sharp variability of data centre loads.
- Who
- Ministry of Power, Grid Controller of India Ltd, BSES Rajdhani Power Ltd
- What
- AI data centres to add 26.3 GW load by 2031-32
- When
- 2031-32
- Where
- India
- Why
- To meet the growing demand for data centre capacity due to the expanding digital economy and AI market.
Urban Data Centres
Rural Data Centres
Location of Data Centres
Urban Data Centres
Data centres should be located near IT hubs for better connectivity and infrastructure.
Rural Data Centres
Data centres should be located near green energy sources to avoid transmission congestion and meet electricity demand through renewable energy.
- Additional Load by 2031-32
- 26.3 GW
- Current Data Centre Capacity
- 1.5 GW (2025)
- Projected Data Centre Capacity by 2030
- 12 GW
- AI-Dedicated Capacity by 2030
- 6,546 MW
- India's Digital Economy Value (2025)
- INR 32 trillion
- Domestic AI Market Projection by 2032
- INR 11.7 trillion
- Data Centre Electricity Demand by 2040
- 20-fold increase from 10 TWh in 2025