Business · Companies · 1 hr ago
Upgraded Yeokji Port opens to support fishing and tourism
Tongyeong's Yeokji Port has completed a major upgrade aimed at supporting fishing, residents and tourism.
The port is in Yeokji-myeon, in South Gyeongsang Province, South Korea.
The 38.6 billion-won project took five years and five months to finish after construction began in June 2021.
New facilities include small-boat docks, a breakwater and a ramp for hauling boats ashore for repairs or shelter.
The upgrade also added passenger-ship berthing space, parks and a fishing pier for visitors.
The expanded small-boat dock beside the fish market will let catches be unloaded and sold at the same time.
The local port authority says it will continue developing ports to meet local needs and serve fishers and visitors.
Yeokji Port in Tongyeong, South Korea, has completed an upgrade intended to support fishing, residents and tourism.
The project cost 38.6 billion won and took five years and five months to complete.
New fishing facilities include small-vessel berths, a breakwater and a slipway for hauling boats ashore.
The project also added passenger-ship berthing facilities, parks, a walking path and a fishing pier.
Officials said the improvements are intended to make the port more useful for fishers and more comfortable for visitors.
- Who
- The Masan Regional Office of Oceans and Fisheries completed the project.
- What
- Yeokji Port was upgraded as a multifunctional fishing port, with facilities for fishing, residents and tourism.
- When
- The project was completed and announced on Nov. 23, 2026.
- Where
- Yeokji Port, Yeokji-myeon, Tongyeong, South Korea.
- Why
- To improve fishing support, convenience for residents and tourism.
This story does not have two clearly opposing sides.
Construction on the Yeokji Port project began.
The Masan Regional Office of Oceans and Fisheries announced that construction was complete.
- Project cost
- 38.6 billion won
- Construction period
- Five years and five months
- Breakwater
- 100 metres
- Small-vessel berths
- 110 metres at the fisheries cooperative, 50 metres at Bulgok village and 50 metres at Gwancheong
- Passenger-ship berthing facility
- 85 metres
- Walking path
- 201 metres
1 source
What people are saying
We improved the port's basic functions and also created a space where passenger-ship users and tourists can rest comfortably.
We will continue developing ports that reflect local characteristics and needs to create ports that satisfy both fishers and tourists.