World · East Asia & Pacific · 59 mins ago
NSW accuses airport metro builders of slowing work amid payment dispute
The NSW government accused the airport metro builders of slowing work on the rail line to Western Sydney International Airport.
The government rejected the Parklife consortium’s claim for $2.2 billion in extra payments, which it says relate to delays, disruption and added work.
The consortium is led by Italian engineering company Webuild, and the dispute has been under way for two years.
The line was meant to open when passenger flights began at the new airport last month, so passengers are using free buses to reach St Marys and connect with Sydney Trains.
The government says the consortium must meet its September 2027 deadline, although Premier Chris Minns has said the opening could slip into 2028.
Sydney Metro says about 80 per cent of the line is complete, and four of its 12 trains are at the stabling yard.
The dispute could also make it harder for the government to move ahead with proposed rail extensions in southwest Sydney.
The NSW government has accused the consortium building the metro line to Sydney’s new airport of slowing work.
The government rejected the consortium’s claims for more than $2 billion in extra payments.
Transport Minister John Graham said the consortium would be held to its contracted completion date of September 2027.
The rail line was meant to open when passenger flights began at Western Sydney International Airport last month.
Sydney Metro chief executive Camilla Drover said about 80 per cent of the line was complete.
- Who
- The NSW government and the Parklife consortium, led by Webuild.
- What
- The government accused the consortium of slowing work and rejected its claims for extra payments.
- When
- The dispute began behind closed doors two years ago; the government made its accusation on November 20, 2026.
- Where
- The metro line runs to Western Sydney International Airport in Sydney.
- Why
- The consortium claims extra costs for unforeseen disruption, delays and increased work scope; the government disputes the claims.
NSW government
Parklife consortium
Extra payments
NSW government
The government rejected claims for more than $2 billion and said it would not make taxpayers pay for unsubstantiated or spurious claims.
Parklife consortium
The consortium claimed $2.2 billion for unforeseen disruption, delay and increased scope of work.
Work and delivery
NSW government
The government accused the consortium of slowing work and said it must meet the September 2027 contracted completion date.
Parklife consortium
The consortium’s account of the work pace and its position on the completion date are not stated.
The Parklife consortium claimed an extra $2.2 billion for disruption, delays and increased work scope.
Passenger flights began at Western Sydney International Airport, but the metro line was not ready to open.
The NSW government accused the consortium of slowing work and rejected its claims for more than $2 billion in extra payments.
The government says the consortium is contracted to complete the line by this date.
- Extra payment claim
- $2.2 billion
- Project completion target
- September 2027
- Construction progress
- About 80 per cent complete
- Trains at Orchard Hills
- 4 of 12
- Consortium leader
- Webuild
What people are saying
We’re not prepared to do it at any cost, and we do expect the consortium to deliver on this contract
We are predominantly in dispute with Webuild. That is disappointing.
We are entering the last stages of civil works and station works, and then we’ll head towards testing and commissioning