Business · Energy & Commodities · 13 hrs ago
Iraq begins work to reopen old oil pipeline to Türkiye
Iraq has begun work to reopen an old oil pipeline to Türkiye that has been closed for 12 years.
Oil Minister Basim Mohammed Khudair launched the work at the IT1 pumping station in Kirkuk.
The pipeline is planned to carry 300,000 barrels a day at first, with a later target of 500,000 after repairs to a second pumping station.
Iraqi engineers and technical teams are carrying out the work using local resources.
Iraq says the restart could expand its crude transport and export capacity and give it more export routes.
The ministry has not given a date for the pipeline to begin operating.
A related Iraq-Türkiye crude oil pipeline resumed operations in September 2025, after being made ready earlier that year following a temporary closure linked to the 2023 earthquakes.
Iraq has begun work to reopen an old oil pipeline to Türkiye that has been closed for 12 years.
Iraqi Oil Minister Basim Mohammed Khudair inaugurated the IT1 pumping station in Kirkuk to start the work.
The pipeline is planned to carry 300,000 barrels a day at first, with a later target of 500,000 barrels a day.
Iraqi engineers and technical teams are carrying out repairs using local resources.
The Oil Ministry said reopening the line would increase crude transport and export capacity and diversify export routes.
- Who
- Iraq’s Oil Ministry, with Iraqi engineers and technical teams, is leading the work.
- What
- Iraq has begun work to reopen an old oil pipeline to Türkiye.
- When
- The report was published on 27 November 2026; the work began with the inauguration of the IT1 pumping station.
- Where
- At the IT1 pumping station in Kirkuk, Iraq, and along the pipeline to Türkiye.
- Why
- The Oil Ministry said reopening the line would increase crude transport and export capacity, diversify export routes and strengthen oil infrastructure.
This story does not have two clearly opposing sides.
The old Iraq–Türkiye oil pipeline had been closed.
Iraq began work to reopen the pipeline with the official inauguration of the IT1 pumping station in Kirkuk.
The pipeline is expected to reach a capacity of 500,000 barrels a day after work at the second pumping station is completed.
- Initial capacity
- 300,000 barrels a day
- Later capacity target
- 500,000 barrels a day
- Pipeline diameter
- 46 inches
- Pumping station
- IT1, Kirkuk
- Pipeline route
- IT1 to IT1A, then to the MS metering station