Alberta approves 920-megawatt plant to power data centre near Edmonton
Alberta’s power regulator approved a 920-megawatt power plant in Sturgeon County, northeast of Edmonton.
The natural-gas-fired plant is being developed by Heartland Power Generation, which is linked to data-centre developer Beacon Data Centers.
The planned data centre would house four halls for AI and high-performance computing, but the regulator’s approval covers only the power plant.
The data centre still needs municipal approval, which may involve rezoning and a development permit.
The plant is expected to start construction in late 2026 and be completed in late 2027.
Samson Cree First Nation was the only active intervenor when the regulator made its decision, after other participants withdrew.
Alberta’s power regulator approved a 920-megawatt natural-gas-fired plant to serve a large data centre northeast of Edmonton.
The plant will be located in Sturgeon County’s Industrial Heartland and built and operated by Heartland Power Generation LP.
The proposed data centre is planned to include four halls for artificial-intelligence and high-performance computing facilities.
The Alberta Utilities Commission regulates the power plant, while the data centre requires municipal approval.
Construction is expected to begin in the fourth quarter of 2026, with completion projected for the final quarter of 2027.
- Who
- The Alberta Utilities Commission approved the project. Heartland Power Generation LP will build and operate the plant.
- What
- A 920-megawatt natural-gas-fired power plant was approved to serve a planned data centre.
- When
- The commission approved it on Friday; the article was published October 26, 2026.
- Where
- Sturgeon County, in Alberta’s Industrial Heartland northeast of Edmonton.
- Why
- The plant is intended to provide power for a large-scale data centre with planned artificial-intelligence and high-performance computing facilities.
This story does not have two clearly opposing sides.
The project was submitted to the Alberta Utilities Commission.
The applicant submitted documents describing the planned data centre’s four data halls.
The Alberta Utilities Commission approved the power-plant application.
Construction of the power plant is expected to begin.
The power plant’s completion is projected.
- Capacity
- 920 megawatts
- Fuel
- Natural gas
- Location
- Sturgeon County, Alberta’s Industrial Heartland
- Data halls
- Four planned
- Planned construction start
- Fourth quarter of 2026
- Projected completion
- Final quarter of 2027