Supreme Court says banks must prove homebuyers defaulted before recovery
The Supreme Court has protected buyers of unfinished flats from immediate loan recovery unless a court first examines the case.
The ruling followed a petition by buyers in the incomplete Krishna housing project in Gurgaon, developed by Raheja Developers, which is in insolvency proceedings.
Under their agreements, banks were meant to release loan money to the builder in line with construction progress.
The court said judges must check whether banks disbursed money as agreed and whether the buyers were actually in default.
Banks cannot seek instalment payments or take coercive action first without that finding.
Many buyers have faced recovery claims despite not receiving their flats, while continuing to pay loan instalments and rent.
The Supreme Court said it may not be able to hear more such cases, and in a similar Bengaluru dispute involving over 4,000 buyers, it directed them to seek relief from the Karnataka High Court.
The Supreme Court said courts must determine whether homebuyers defaulted before directing them to repay housing financiers.
It said courts must examine whether banks disbursed loans to builders according to construction progress and the terms of tripartite agreements.
The ruling came in a petition by homebuyers in the incomplete Krishna housing project in Gurgaon, developed by Raheja Developers.
The court directed that no coercive action be taken against the petitioners or similarly placed buyers before that examination.
It also protected buyers in a separate Bengaluru project and asked them to seek further relief from the Karnataka High Court.
- Who
- The Supreme Court, in a bench led by Chief Justice Surya Kant, ruled on a petition by homebuyers.
- What
- Courts must assess whether buyers defaulted and examine the bank-builder relationship before ordering repayment or taking coercive action.
- When
- Thursday, November 19, 2026, according to the article’s publication date.
- Where
- The ruling concerned the Krishna housing project in Gurgaon. The court also referred to a separate case in Bengaluru.
- Why
- The buyers said recovery proceedings had begun even though they had not received their flats. The court said banks’ loan disbursements must be examined against construction progress and tripartite agreements.
Homebuyers
Banks and financiers
Recovery before delivery of flats
Homebuyers
Buyers said recovery proceedings were being pursued despite their not having received their flats.
Banks and financiers
Banks filed recovery suits against buyers over unpaid loans.
Loan disbursement and buyer liability
Homebuyers
The court said buyers should not be ordered to pay unless a court first finds they defaulted and examines whether disbursements followed construction progress and the agreement.
Banks and financiers
The agreements provided for financiers to disburse loans directly to builders in proportion to construction progress.
A Supreme Court bench ordered a CBI inquiry into alleged collusion between builders and banks involving the tripartite subvention scheme.
The Supreme Court issued its ruling in the Krishna housing project case and protected buyers in a separate Bengaluru case from possible recovery proceedings.
- Project
- Krishna housing project, Gurgaon
- Developer
- Raheja Developers
- Bench
- Chief Justice Surya Kant, Justice Joymalya Bagchi and Justice V Mohana
- Bengaluru case
- More than 4,000 homebuyers; buyers had paid 95% of the flat cost
- Court direction
- No coercive action before determining whether buyers defaulted and examining the bank-builder relationship
What people are saying
It is the bounden duty of the commercial court to determine the nexus between the builder and bank officials and to see whether the bank disbursed the loan amount to the builder strictly in terms of the tripartite agreement.
We direct the civil court not to take any coercive action against the petitioners or similarly placed homebuyers without first determining the above-mentioned issue.