Politics · Australia · 2 days ago

Tasmanian EPA seeks to join appeal over data centre generators

Tasmanian EPA seeks to join appeal over data centre generators

Firmus Technologies is building a 288-megawatt AI data centre in George Town, in northern Tasmania.

The town council approved the project earlier this year, after the state Environmental Protection Authority decided it did not need an environmental assessment.

The approval allows the site's 276 diesel generators to run only at limited times, such as during emergencies or routine tests.

Firmus has appealed that restriction, saying it wants to use the generators at times to support the electricity supply and maintain reliable operations.

The EPA says it understood the generators would be used mainly during power failures, and that the wider use Firmus now seeks could have changed its decision about assessing the project.

It has asked to join the appeal before the Tasmanian Civil and Administrative Tribunal, warning that the generators' environmental risks may not have been properly assessed.

The tribunal is considering Firmus's appeal.