Business · Companies · 2 hrs ago
Frux Capital backs Proxity’s second Portuguese data centre with nearly €20m
Frux Capital will provide nearly €20 million to help Proxity Data Centers develop a data centre in Loures, near Lisbon.
It is Proxity’s second data centre in Portugal.
Proxity is part of Quantum Next, while Frux is a private-debt manager that is expanding from real estate into data centres.
The funding will support the purchase of land and planning and infrastructure work, helping move the project toward being ready to build.
The site has grid connection capacity for a campus of more than 100 megawatts in its initial phase, with construction investment expected to approach €800 million.
Work is planned to start in the second half of 2027, and the centre is expected to begin operating in 2029.
Frux Capital has agreed to provide nearly €20 million to Proxity Data Centers for its second data centre in Portugal.
The project is in Loures, in the Lisbon metropolitan area.
The financing will support land acquisition and the project’s urban, environmental and infrastructure development.
The planned campus is expected to have more than 100 MW of capacity in its initial phase.
Work is scheduled to begin in the second half of 2027, with operations planned for 2029.
- Who
- Frux Capital is financing Proxity Data Centers, which is part of the Quantum Next group.
- What
- Frux agreed to provide nearly €20 million for Proxity’s second data centre in Portugal.
- When
- The agreement was reported on 19 November 2026. Work is planned to begin in the second half of 2027.
- Where
- Loures, in the Lisbon metropolitan area, Portugal.
- Why
- The funding is for acquiring land and developing the project’s urban, environmental and infrastructure works.
This story does not have two clearly opposing sides.
The financing agreement was reported.
The first project works are scheduled to begin.
The data centre is planned to enter operation.
- Financing
- Nearly €20 million
- Project location
- Loures, Lisbon metropolitan area
- Initial campus capacity
- More than 100 MW
- Planned construction investment
- Nearly €800 million
- Planned start of works
- Second half of 2027
- Planned operations
- 2029