Business · Energy & Commodities · 1 hr ago

South Africa delays private grid investment tender until 2027

South Africa delays private grid investment tender until 2027

South Africa has delayed a tender that would invite private investors to build electricity transmission lines.

The request for proposals is now expected in the second quarter of 2027, rather than the third quarter of 2026.

The programme is intended to bring investment into the grid and help move electricity from areas where it is generated to where it is needed.

The grid is already limiting the connection of new electricity generation.

Investors will deal with a new transmission operator that is still being established and does not yet have its own balance sheet or credit history.

A credit guarantee vehicle is being prepared to help protect investors from credit risks, and the delay gives institutions time to get the process ready.

The tender’s first phase calls for 1,164 kilometres of new lines, while the transmission company plans 14,500 kilometres by 2034.

The government has not set out a full timetable for choosing bidders and reaching financial close, when construction can begin, and the new grid infrastructure is unlikely to be operating by the end of the decade on the current timeline.