Indonesia reports three of five West Java suspension bridges complete
Indonesia’s Public Works Ministry is building five suspension bridges in rural areas of West Java.
Three bridges have been handed over: Sukasari in Purwakarta, Cibeber II in Bogor and Mertajaya in Tasikmalaya.
The two remaining projects are Mulangsari in Karawang and Tugujaya in Bogor, both at late stages of construction.
Mulangsari is targeted for completion by 25 November, while Tugujaya is expected to be handed over on 24 November.
The bridges are intended to make travel and farm deliveries easier and improve access to public services.
The ministry says better connections could support village economies and extend access in areas that have been harder to reach.
Indonesia’s Public Works Ministry says three of five suspension bridges being built in West Java have been completed and handed over.
The completed bridges are in Purwakarta, Bogor and Tasikmalaya regencies.
Two other bridges, in Karawang and Bogor, are in the final stages of construction.
The ministry says the bridges are intended to improve local mobility, connect communities and support economic activity.
- Who
- Indonesia’s Public Works Ministry is building the bridges through its DKI Jakarta–West Java National Road Implementation Agency.
- What
- Three of five suspension bridges in West Java have been completed and handed over.
- When
- The report was published on 10 November 2026. The three handovers took place between 14 July and 3 November 2026.
- Where
- West Java, Indonesia, in Purwakarta, Bogor, Tasikmalaya and Karawang regencies.
- Why
- The ministry says the bridges will improve connectivity and mobility, ease the movement of agricultural products and improve access to public services.
This story does not have two clearly opposing sides.
The 60-metre Sukasari suspension bridge in Purwakarta Regency was handed over.
The 40-metre Cibeber II suspension bridge in Bogor Regency passed provisional handover.
The 80-metre Mertajaya suspension bridge in Tasikmalaya Regency was officially handed over.
The ministry reported that three of the five West Java bridges had been completed and handed over.
The Tugujaya bridge in Bogor Regency is targeted to undergo provisional handover.
The Mulangsari bridge in Karawang is targeted for completion.
- Completed bridges
- 3 of 5
- Sukasari bridge
- 60 metres; handed over on 14 July 2026
- Cibeber II bridge
- 40 metres; provisional handover on 28 October 2026
- Mertajaya bridge
- 80 metres; handed over on 3 November 2026
- Mulangsari bridge
- 120-metre span; targeted completion on 25 November 2026
- Tugujaya bridge
- 60-metre span; provisional handover targeted for 24 November 2026