Key tunnel completed on Guangxi section of Nan-Zhu high-speed railway
Workers completed the Wensi Tunnel on the Cenxi East-to-Guangdong border section of the Nan-Zhu high-speed railway in Guangxi, southern China.
The tunnel is 4.77 kilometres long and runs through mountainous terrain with difficult and unstable rock.
Its completion clears the way for bridge-beam installation and track construction, and helps keep work on the railway section moving.
The tunnel was a key route for installing bridge beams, and its construction involved risks from possible collapses and sudden water inflows.
Six of the section’s eight tunnels are now complete, while work continues on the remaining two.
They are expected to be completed in early 2027.
Once the section is open, it is intended to strengthen transport links between Guangxi and the Guangdong-Hong Kong-Macao Greater Bay Area.
The Wensi Tunnel on the Cenxi East-to-Guangdong-Guangxi provincial boundary section of the Nan-Zhu high-speed railway was completed on November 22.
The 4,768.79-metre tunnel is in Guiyi Town, Cenxi, Wuzhou, Guangxi.
Its completion clears the way for box-girder installation and later track work.
Six of the section’s eight tunnels have been completed, while work continues on the other two.
The remaining tunnels are expected to be completed in early 2027.
- Who
- Guangxi Transportation Investment Group invested in the project; China Railway No. 5 Engineering Group built the tunnel.
- What
- The Wensi Tunnel was completed, clearing the way for later railway construction work.
- When
- November 22, 2026.
- Where
- Guiyi Town, Cenxi, Wuzhou, Guangxi, on the Cenxi East-to-Guangdong-Guangxi boundary section.
- Why
- The tunnel is a key route for box-girder installation, and its completion enables subsequent construction work.
This story does not have two clearly opposing sides.
The Wensi Tunnel was completed.
The other two tunnels on the section are expected to be completed.
- Tunnel length
- 4,768.79 metres
- Maximum burial depth
- About 181.2 metres
- Tunnels completed
- 6 of 8 on the section
- Remaining tunnel completion
- Expected in early 2027